INSTITUTE
OF ARCHAELOGY - SURVEY
HOME
| SITE
INDEX
ARCHAEOLOGY
SOUTH-EAST, INSTITUTE OF ARCHAEOLOGY, UNIVERSITY
COLLEGE LONDON
Site
The Old Steam House, Lime Park, Herstmonceux,
East Sussex
NGR
TQ 6365 1223
Project
Ref
1146
Date
of Survey
29/9/99
This
revision
30/9/99
THE
OLD STEAM HOUSE,
LIME
PARK, HERSTMONCEUX, EAST SUSSEX
(Centred
at TQ 6365 1223)
COMMISSIONED
BY
EAST
SUSSEX COUNTY COUNCIL
Project
REF. 1146
by
by
David Martin FSA
IHBC MIFA
&
Barbara
Martin AIFA
INTRODUCTION
The
report which follows was commissioned by Andrew
Woodcock, County Archaeologist for East Sussex.
The brief was to carry out a rapid inspection of
The Old Steam House, Lime Park, Herstmonceux, with the
aim of ascertaining as far as possible how much of the
original fabric of the two-gabled part of the building
survives, and to identify clues as to its original form.
The survey excluded any evidence for plant,
unless forming part of the standing elements of the
structure.
The
inspection was carried out by David and Barbara Martin,
Historic Buildings Officers with Archaeology South-East,
University College London, on Wednesday 29th
September 1999 and was limited to three-and-a-half hours
on site.
LOCATION
The
Old Steam House is centred at grid reference TQ 635
1223, approximately 150 metres to the north of the house
known as Lime Park. And immediately to the north-west of
a dwelling now called ‘The Old Rectory’.
It comprises a complex of attached single-storeyed
tin clad structures, part aligned with its roof ridges
running NE-SE (for convenience hereafter assumed to be
N-S) and part aligned with its roof ridge running SE-NW
(for convenience hereafter assumed to be E-W) – other
sections have gently sloping mono-pitched roofs.
That part of the complex which forms the subject
of this present report forms the northern element of the
building as it currently stands and consists of a single
block covered by two adjoining parallel roofs, both with
their ridges running north-south (figure 2).
Formerly, there was a further range attached to
the north of the complex, but only the foundations of
this now survive.
THE
LIMITATIONS OF THIS REPORT
Interpretation
of the structure was based upon a visual inspection and
(apart from removing two small areas of loose coverings)
included no intrusive techniques.
Externally the majority of the walls and all the
roofs are clad in corrugated tin, whilst internally
below roof level most of the constructional details of
the walls are today masked by modern sheet claddings.
Only within a small area of the north wall is a
section of framing
-
1 -
ARCHAEOLOGY
SOUTH-EAST, INSTITUTE OF ARCHAEOLOGY, UNIVERSITY
COLLEGE LONDON
Site
The Old Steam House, Lime Park, Herstmonceux,
East Sussex
NGR
TQ 6365 1223
Project
Ref 1146
Date of Survey
29/9/99
This revision
30/9/99
Visible.
With the exception of the roof trusses and
purlins, most of the constructional detail within the
attic areas is masked by original boarding.
Only within the southern gable of the western
roof and small areas where boarding within the roof
slopes is missing is any constructional detail visible.
These factors greatly hindered assessment of the
extent of the original fabric and interpretation of the
structures sequence of development and original form.
These restraints should be borne in mind when
considering the findings presented below.
CARTOGRAPHIC
AND DOCUMENTARY EVIDENCE
The
building is not shown on the 1899 25” O.S. plan
surveyed in 1872/3 and fully revised in 1898 (O.S.
Sussex Sheet 56/11 – 2nd Edition).
A building is indicated upon the site by 1909 (Ibid
3rd Edition) but this scale only c.8.00
metres east-west x c4.00 metres north-south (excluding a
small southward projection at the eastern end): the core
section of the surviving building measures 11.75 metres
x 6.25 metres. In
addition to this size variation, the building depicted
on the 1909 O.S. plan is shown with a much larger gap
than now between it and the adjacent Old rectory, whilst
its rear (northern) wall is shown further south than
that of the present building.
Even allowing for inaccurate surveying, the
number of variations between the 1909 depiction and the
present building make it all but certain that the 1909
representation is of a building which pre-dated the
present structure.
No
later editions of the relevant 25” O.S. plan (showing
revisions of between 1910 and 1940) were readily
available at the time this report was written, and thus
it is not currently known when the present building was
first depicted on the 25” O.S. plans.
However, a report in the Sussex Express for
October 10th 1913 states:-
“Few
villages of the size of Herstmonceux can boast of being
so up to date as to have electricity installed, not only
in the streets, but also in the private houses.
This was made possible by the enterprise of Mr C
W von Roemer [the owner of Lime Park], who by his
electric plant supplies electricity by motor.
During
the week demonstrations in cooking by electricity have
been given… and Mr von Roemer has generously offered
to fit an electric stove in any house in the parish
free, and to make a charge of 11/2d [per] unit for the
use of the electricity.
Many people in the village have already accepted
the offer, and the results obtained by this new means of
cooking are very satisfactory”
[Quote supplied by Nelson Kruschandl, via Andrew
Woodcock].
There
can be no doubt from the physical evidence of the bases
and pits for former electricity-generating plant
remaining on site, of artefacts relating to electricity
generation, and from the signed affidavit of Ronald
Saunders whose father worked the plant and who remembers
the equipment in situ, that the electricity
generating plant referred to in the
-
2 -
ARCHAEOLOGY
SOUTH-EAST, INSTITUTE OF ARCHAEOLOGY, UNIVERSITY
COLLEGE LONDON
Site
The Old Steam House, Lime Park, Herstmonceux,
East Sussex
NGR
TQ 6365 1223
Project
Ref 1146
Date of Survey
29/9/99
This revision
30/9/99
1913
newspaper article was located within the building which
is the subject of this present report.
Although a precise date for the building is not
possible based on the typological evidence, the
surviving architectural details are entirely consistent
with an early-20th-century date.
It therefore seems fair to suggest that the
building shown on the 1909 25” O.S. plan was purposely
rebuilt in or a little before 1913 in order to house the
electricity generating plant.
As will be noted below, some alterations
(currently not entirely understood) were made to thee
building subsequently.
ARCHITECTURAL
DESCRIPTION
The
section of building which forms the subject of this
present report is a rectangular structure measuring
11.75 metres (38’6”) east-west and 6.25 metres
(20’6”) north-south.
It is single storeyed and is covered by two
parallel roofs aligned north-south and divided by a
central valley. There
is today an attic floor supported by joists inserted
during the 1990s, though these replaced a loosely-laid
earlier attic floor [pers. Comm. Nelson Kruschandl].
The visible structural evidence suggests that
this earlier floor was not original and that the
building was initially open to its roof.
The storey height from floor to underside of the
tiebeam is 2.73 metres (9’0”).
As
far as can be seen from
the visible evidence, this section of the
building is entirely of timber stud construction built
off a brick ground wall.
Horizontal rails are morticed and tenoned (joints
pegged) between the studs in order to carry vertical
internal and external boarding.
The boards, where they survive, are beaded.
Most of the studwork and noggings are 104mm x
52mm (4” x 2”) scantling, but incorporated into the
walls are heavier studs 104mm x c.225mm (4” x 9”)
[only one of these (in the north wall) was visible:
Nelson Kruschandl knows others exist}.
A small area of structural detail is visible at
the north-western corner, and here there is no corner
post, but instead a series of heavy horizontal noggings
have been roughly sawn through and clearly formerly
extended westwards.
They still support external boarding identical to
that elsewhere in the building.
Insufficient is visible to ascertain why the wall
detail is varied at this point, but the westward
extension is known to have formed part of a
now-demolished range which stood to the north.
Although it would need to be confirmed by
intrusive investigation, it would appear from the
available evidence that this northern range of building
was of the same date as that section which forms the
subject of this report.
Both
sections of roof within that part of the building here
under investigation are of
similar construction, but with some minor
variations in detail (see figure 4 and below).
They are framed in three bays and have studwork
gables to north and south.
They are of textbook kingpost construction with
splay-cut jowls at the base of the posts (to support
struts) and similar jowls at the head (carrying the
inset principal rafters).
The principal rafters and purlins are exposed to
view, but the common rafters which the purlins carry are
hidden from view by beaded under-boarding identical to
that used on the walls.
Investigation
-
3 -
ARCHAEOLOGY
SOUTH-EAST, INSTITUTE OF ARCHAEOLOGY, UNIVERSITY
COLLEGE LONDON
Site
The Old Steam House, Lime Park, Herstmonceux,
East Sussex
NGR
TQ 6365 1223
Project
Ref 1146
Date of Survey
29/9/99
This revision
30/9/99
through
small broken areas allow the constructional details to
be ascertained. There
are no wallplates, but instead the common rafters are
carried over the backs of the lower tier of purlins.
In addition, there is a central line of purlins.
At the head the common rafters meet at a
ridgeboard. The
common rafters are set at approximately 660mm centres.
Located centrally within each slope of each bay
within the western roof is an (apparently original)
rooflight. These
are an identical number of rooflights within the eastern
roof, but these are located less symmetrically.
Some
original joinery details still survive.
The external and internal boarding and the
rooflights have already been mentioned.
In the northern gable of the western roof is a
shuttered hatch. The
shutter is top hung, opens inwards and was operated from
the ground by a pulley (still extant).
In the southern gable of the same roof and within
the northern gable of the eastern roof survive original
four-pane windows, and there is another original window
towards the eastern end of the northern ground-floor
wall. Many
of the openings retain their moulded architraves, whilst
the ground-floor window also retains external
architraves.
The
ground floors contain evidence in the form of plinths,
pits and ducts as to the original form of the power
plant, but these are beyond the scope of the present
report. In
the main, the floor within the western part is of flag
stones (interrupted by plant pits etc and at one
point made good where a machine base has been removed),
whilst the eastern part is of concrete.
Between the two is an infilled internal ramp
which allowed access to the eastern and western rooms.
The eastern concrete floor incorporates a
160-170mm upstand along its eastern and southern sides,
together with a drain-down gully in the south-west
corner and a raised plinth in the north-east corner.
According to Ron Saunder’s signed affidavit,
when he knew the building this area was used to house
accumulators.
There
is some structural evidence to hint that the section of
building under investigation is of two phases of
construction, though if so the two phases are of very
similar date. The
evidence, which is found both in the constructional
details and in the building’s design, is not
conclusive. The
variations in constructional details are slight, but may
be significant. The
joints to the roof trusses within the eastern roof are
pegged, though those within the western roof are not,
whilst in the western roof the struts meet the principle
rafters in line with the central purlins, whereas within
the eastern roof they joint into the principle rafters
above the central purlins.
The design anomalies are more puzzling.
Although the two roofs run parallel to one
another (being separated by a central valley) they are
of different spans and heights – the overall span of
the western roof is 5.50 metres (18’0”) compared
with 6.25 metres (20’6”) for the eastern roof.
If of one period, this would only make sense if
there was an internal partition beneath the central
valley, but such an interpretation is not supported by
the surviving evidence – the widest room was beneath
the narrowest pitch and encroached in to the eastern
roof pitch. Taken
together these two pieces of evidence suggest that the
structure was built in two phases and that when the
addition was made the internal layout was modified.
Unfortunately, because the structural detail is
not visible,
-
4 -
ARCHAEOLOGY
SOUTH-EAST, INSTITUTE OF ARCHAEOLOGY, UNIVERSITY
COLLEGE LONDON
Site
The Old Steam House, Lime Park, Herstmonceux,
East Sussex
NGR
TQ 6365 1223
Project
Ref 1146
Date of Survey
29/9/99
This revision
30/9/99
The
evidence to confirm or deny this hypothesis is not
currently available.
If the structure is indeed of two phases, then it
is the eastern section which is the earlier part, for
the two tiebeams which cross the building east-west are
each formed from two timbers (one to the eastern roof
and one to the western roof).
These two sections of timber extend past one
another and are joined together by means of three bolts.
In both instances the eastern section of tiebeam
terminates in line with the valley, whereas the western
section projects by some distance into the eastern roof.
There are slight traces of stain on the side
faces of the eastern tiebeams, a little from the end,
possibly indicating the ghost of a removed wall.
Given the doubts, for convenience both elements
of the section of building under investigation are
deemed to have been constructed during phase 1, but the
eastern (possibly earlier part) will be referred to as
being phase1A and the western (possibly later part) as
phase 1B (figure 2).
Interpretation
of the internal layout is hampered by the degree to
which the structural details are hidden.
One alteration causes no problems, having been
made during the last five years or so.
This involved removing the wall between the
western room and central service ramp and replacing it
by a new wall some distance to the west, thereby
narrowing the western room and widening the central area
[pers. comm. Nelson Kruschandl – compare
figures 3A and 3B].
The line of the earlier wall is clearly visible
as a stain on the tiebeams.
If the structure is indeed of two main phases,
then even this earlier wall may have dated from phase
1B, replacing a phase 1A running beneath the western end
of the eastern tiebeams.
There is some slight staining on the side of the
phase-1A tiebeams to support this conclusion, but the
evidence is far from conclusive.
There
is structural evidence to show that there has been
modification to the layout within the eastern part of
the building. A
heavy structural post in the northern wall and located
approximately beneath the ridge line of the eastern roof
is notched for a heavy (c150mm x c. 310mm) bearer
running north-south immediately beneath the tiebeams.
Although, now hidden, there is a corresponding
post in the south wall [pers. comm. Nelson
Kruschandl]. The
line of the bearer is shown as a stain on the underside
of the southern tiebeam – the soffit of the northern
tiebeam is masked by later work.
Further, the marks of a light fitting on the
southern tiebeam are located centre span between the
stain left by the bearer and the eastern wall.
As additional proof, the southern upstand on the
concrete floor is made good on the line of the removed
bearer. Given
this evidence, there can be little doubt that the
removed bearer formed the headplate of a now lost
partition (figure3C).
What is clear from the evidence contained within
the structural ground floors is that the modified layout
as shown in figure 3B belonged to the period when the
building was still in use for the generation of
electricity.
-
5 -
ARCHAEOLOGY
SOUTH-EAST, INSTITUTE OF ARCHAEOLOGY, UNIVERSITY
COLLEGE LONDON
Site
The Old Steam House, Lime Park, Herstmonceux,
East Sussex
NGR
TQ 6365 1223
Project
Ref 1146
Date of Survey
29/9/99
This revision
30/9/99
A
BRIEF NOTE ON OTHER PARTS OF THE BUILDING
Attached
to the north of the section under investigation, and
projecting slightly to the west, was a second attached
building or range.
This has been demolished, though its foundations
and plant bases still survive.
From the structural evidence visible at the
north-western corner of the surviving building (see
above) this demolished range appears to have been
contemporary with the surviving phase-1B section.
Attached to the south wall of the section under
consideration is a further building or range, roofed
east-west and apparently representing an addition to the
main part made whilst the building was still in use as
an electricity generating station.
Beyond this to east and south are later ‘flat
roofed’ additions (figure 2).
At the extreme southern end of the complex is a
‘faggot store’: located upon the site of a building
shown on the 1909 25” O.S. plan and may incorporate
some external brickwork of that period.
CONCLUSIONS
Despite
alterations to the original internal layout, there can
be little doubt that much of the original structure
still survives. Despite
some minor modifications, the roof structure and
internal finishings within the roof void remain largely
intact. Regarding
the external walls, the west wall has been completely
rebuilt during the last 10 years, but although elsewhere
within the external walls little of the structural
evidence is visible, the survival of early external
boarding beneath the later corrugated coverings indicate
that most of the early structure still remains.
To judge from the small area exposed (which shows
evidence of a lost partition) this hidden detail will
contain much information which would allow the
development of the building to be better understood.
Likewise, although excluded from the present
report, the floors contain much significant surviving
evidence.
It
will be clear from the contents of this report that,
although the building was in use for the generation of
electricity over a relatively short time between
1909x1913 [O.S. plan and newspaper report] c.. 1925
[sworn affidavit says about 1920, but from other
evidence probably nearer 1930] the plant appears to have
developed and expanded during that period.
The generation of electricity lies outside the
competence of the present writers, but it is interesting
to note that the 1913 newspaper article refers to the
generation of electricity ‘by motor’ whereas the
sworn affidavit relating to the plant late in its life
refers to generation by steam engine.
Was the take-up by the local community sufficient
to require an initial small-scale operation to be
considerably enlarge and improved, thus accounting for
the apparent major expansion hinted by the architectural
remains?
This
present report is limited to an investigation of the
standing remains of one part of the surviving complex ad
is entirely dependant upon the visible evidence.
The significance of the remains which survive
lies outside the scope of this document.
-
6 -
Herstmonceux
Electricity Generating Works Circa. 1900 - 1936
Links:
Introduction
| Instructions
| ISBN
| Batteries
| Boiler
Room | Floor
Plan | Ron
Saunders
Industrial
Revolution
| Lime
Park | Machinery
| Map
| Power
House | Argus
1999
Public
Supply | Roof
Construction | Rural
Supply | Sussex
Express 1913 |
Conclusion
Archaeology
South East |
East Sussex CC
| English Heritage
| SIAS
| Sx Exp 1999
Herstmonceux
Links Page
Wentworth
House
|